As you may have already noticed, the construction for 1445 Wellington St. West began this week.
Although a pre-construction meeting is being planned by Jeff Leiper's office, unfortunately, Mizhari is moving ahead before this pre-construction meeting can take place. Here is the initial construction schedule:
Timeline:
Week of
October 21, 2019:
October
21 – Fast Fence
Around 1445 Wellington installed by EOD
October
22 – 1445 Demolition
Begins
October
25 – 1445
Demolition Tentative Completion
October
25 – Backfill
Demolition
Week of
October 28, 2019:
October
30 – Ribbon Cutting
Ceremony
October
31 – Bell will
begin to remove poles at North-side of site (behind Sales Center)
October
31 – Disconnects
scheduled for 1451 Wellington
November
1 – Mobilization of
Drill Rig
Week of
November 4, 2019:
November
4 – Mobilization
for Demolition of 1451 Wellington
Sadly, the parklette is being impacted by the construction. Mizhari decided that in order for them to build this
project, they need to stage in the parklette, which will require the trees to
be cut down. Clearly, the WVCA is not happy with this decision. The alternative option
would have seen them stage on the Wellington West sidewalk and part of the
road. Obviously, this is not ideal as well and would greatly impact the safety of pedestrians, cyclists and drivers.
Mizrahi is paying the City for the tree loss and new trees will be planted in
the parklette when that is being developed.